Construction Update: October 2, 2025
Posted on
Progress on the Good Faith Chapel continues with almost sixty craftspeople on-site each day. This past month saw the near completion of exterior stone and glass installation. In addition, the installation of cleating for millwork on the walls and ceiling began. Slate continued to be installed on the roof, exterior, and ambulatory walls; and mechanical, electrical, and sprinkler work continued.
In October, we expect the final windows and doors to be installed, air handling systems to begin operation, and millwork installation to commence. In addition, interior handrails for balcony and bridge are scheduled to be installed. The supporting wall system for the LED screens will also be completed.
Thanks to all of the parishioners and friends who continue to financially support the Good Faith Chapel, we have now reached almost 300 donors exceeding $30,100,000.