Construction Update: November 6, 2025
Posted on
Our hearts are full with the progress on the Good Faith Chapel. This past month final windows and doors were installed (dried in!), air handling systems started, electrical systems turned over, and millwork installation commenced. In addition, interior handrails for balcony and bridge were installed and the supporting wall system for the LED screens was completed.
In November, we expect to continue wood trim installation, begin finish metal installation, begin low-voltage wiring for LED walls, and continue exterior and internal vertical slate.
Thanks to all of the parishioners and friends who continue to financially support the Good Faith Chapel, we now need less than $750,000 to reach our goal of $31,000,000!